Development and Building permitting is the main instrument for controlling or managing physical development. Development permit in this context refers to permits issued in relation to planning and building applications Effective development management promotes orderliness, convenience of movement, public safety and enhanced economic development.

Development Permitting deals with the correct use the land, the appearance of the proposed building and the effect that the development will have on the general environment and neighbouring properties.

A Building Permit allows construction of buildings or structure to proceed on condition of compliance to building code.

  • Erection of any building or structure except those exempted by law
  • Making structural alteration and or transformation (renovation) to a building
  • Hoarding of property
  • Planning permission in principle
  • Change of use/rezoning
  • Sub-division or amalgamation of plot
  • Extension of time
  • Certificate of Completion for habitation
  • Temporary structure permit
  • Regularization of existing structures
  • Extension of existing building
  • Demolition permit
  • Submit your full set of application to the Physical Planning Department
  • Attach completed  land ownership  document from Lands Commission
  • Attach four copies of architectural drawings signed by a certified Architect
  • Attach four copies of structural drawings signed by an Engineer
  • Proposed development must conform to zoning status
  • A certified soil test report
  • Fire certified report including drawings from the Ghana National Fire Service
  • Environmental Protection Agency Permit
  • Structural integrity report in case construction development has already commenced or is completed

Requirements Checklist

  • Building Permit Application Form –one(1) copy
  • Title Search one(1) copy
  • Indenture or Deed of assignment or Land Title Certificate one(1) Copy 
  • Architectural Drawing four(4) copies
  • Structural Drawings four(4) copies)
  • Structural Calculation Repor four(4) copies)  
  • Fire Report three(3) copies   
  • Mechanical or Services Drawing four(4) copies  
  • Geotechnical Report Structural Integrity Report three (3) copies  
  • Environmental Permit one(1) copy     
  • Traffic Impact Assessment (T.I.A) (three (3) bound copies)
  • Hydrological Services Report (if requested) (three (3) bound copies
  • Property Rate 

Apart from the cost of the Permit Application Form and Processing Fees, all other costs are arrived after going through each process based on the fee fixing resolution of the Assembly for that year.